Pilot 01: A 143 kWp Rooftop System as a Live Proof-of-Concept.
Sugar Beach, Mauritius is the first asset run through the full SEGA-EOP screening pipeline under VMR0017 — a working demonstration of evidence-first discipline, not a claim of issued credits.
Ten evidence gates, transparently tracked.
Each gate must be cleared with evidence before the asset can advance. Current status is shown honestly — including where evidence is still open.
- 1Asset ownership & environmental rightsIn Review
- 2Methodology applicabilityIn Review
- 3AdditionalityNot Started
- 4Baseline & grid-factor evidenceEvidence Gap
- 5Metering / MRV readinessIn Review
- 6Double-counting / REC or I-REC controlsNot Started
- 7VVB pre-assessmentNot Started
- 8Verra registration pathwayNot Started
- 9Cost-to-issue / economicsIn Review
- 10Compliant market & settlement architectureNot Started
Proof of process, not proof of profit.
Real asset, real data
A commissioned 143 kWp system provides genuine generation and metering data to test the MRV design end-to-end.
Metering-first
Locking the meter and MRV architecture early is the gate that determines whether a credible claim is even possible.
VVB-ready packaging
The output is a submission package structured for independent VVB pre-assessment — the honest test of readiness.
Note: Emission factor, volumes and gate outcomes shown are illustrative placeholders pending verified project evidence. Strategic concept — subject to AU-ASRIC approval, Verra eligibility, independent VVB validation / verification, legal and registry requirements, and applicable jurisdictional regulation.